Project planning · 9 min read

What connectivity does a new site or infrastructure project need?

A plain-English guide to defining connectivity requirements, choosing suitable products and building realistic cost and programme allowances for a new site.

Prepared by CROSSLast reviewed 14 August 2026
Direct answer

A new site should not begin by choosing a carrier or product. First review any existing fibre, ducts, services and handover points, then define what the connection must support, the required capacity, failure tolerance, destinations, programme, budget and support model. Those requirements can be translated into a primary service, backup path, route, handover design and commercial specification.

Start with the operational need

The correct product depends on what the site is doing. A construction compound that needs temporary access has a different requirement from a data centre, a telecom mast, a BESS project or an operating network node. Begin by defining the systems that depend on the connection and the consequence of an outage.

Typical uses include corporate access, internet connectivity, cloud services, operational technology, telemetry, CCTV, voice, remote maintenance, customer traffic, replication between sites and high-capacity transport into a wider network.

Important: “We need fibre” is not yet a specification. Fibre describes the physical medium, not the service, capacity, resilience, support model or commercial outcome.

The questions the project team should answer

  1. What must the connection support?List the applications, systems, destinations and operational dependencies.
  2. How much capacity is required?Define the initial need, expected growth and any peak or burst requirement.
  3. How much failure can the project tolerate?Decide whether a single path is acceptable or whether diverse primary and backup services are required.
  4. Where must traffic go?Internet, cloud region, carrier hotel, control centre, data centre, core POP or another project site.
  5. When must it be live?Work backwards from the operational date and include surveys, wayleaves, civils, access and testing.
  6. Who will operate it?Clarify whether the client wants a managed service or has the capability to operate optics, routing and faults internally.
  7. What commercial model is acceptable?Balance one-off construction cost, recurring charges, contract length, scalability and ownership.

Likely product options

ProductBest suited toKey question
Dedicated Internet AccessBusiness-grade internet with defined bandwidth, support and service levelsIs resilient internet required, and who will provide routing, IP addressing and DDoS protection?
Managed EthernetPrivate point-to-point or multipoint connectivity between known locationsDoes the service need to connect sites rather than provide internet access?
WavelengthHigh-capacity transport, commonly 10G, 100G or 400GAre the end points fixed and is a managed optical service preferred?
Dark fibreHigh control, scalable capacity and long-term strategic routesCan the client operate the optics and accept responsibility for the active layer?
MicrowaveMast sites, remote locations, rapid deployment or route diversityIs clear line of sight available and is spectrum, capacity and weather performance suitable?
Mobile or satelliteTemporary service, backup, remote telemetry or sites where fixed infrastructure is unavailableWill coverage, latency, data allowance and service assurance meet the operational need?

Several products may be used together. For example, a site may use a fibre-based primary service and an independently routed microwave, mobile or satellite backup.

What the estimate must include

A credible estimate separates the monthly service charge from the work required to reach and prepare the site.

  • Carrier installation and connection charges
  • Monthly or annual recurring service charges
  • Excess construction charges and civils
  • Duct, chambers, fibre, splicing and testing
  • Wayleaves, consents and private-land access
  • Internal containment, meet-me room and power requirements
  • Network equipment, optics, routing and security
  • Project management, surveys and design
  • Testing, acceptance and contingency
  • Future upgrades, contract changes and termination exposure

A practical procurement sequence

01Review what already exists

Existing fibre, ducts, services, handovers, contracts, capacity and resilience.

02Define the outcome

Operational use, capacity, destinations, resilience, programme, budget and support.

03Screen the site

Nearby networks, viable corridors, likely handovers and route constraints.

04Specify and procure

A clear response schedule so carriers quote the same requirement.

05Manage delivery

Surveys, access, wayleaves, civils, installation, testing and handover.

06Operate and assure

Monitoring, fault escalation, incident reporting, service reviews and lifecycle management.

Where CROSS fits

CROSS can support one stage or act as the accountable connectivity workstream from the existing-infrastructure review through carrier procurement, live-service handover and optional operational assurance. The client does not need to know the product before engaging us.

Frequently asked questions

Common questions

Do we need fibre at every new site?

No. Fibre may be the preferred primary service for capacity or assurance, but microwave, mobile or satellite can be appropriate for temporary use, backup or remote sites. The choice should follow the operational requirement.

Can CROSS give an initial view before the site is acquired?

Yes. A desktop screen can identify the likely carrier landscape, obvious route constraints, probable product options and the questions that need deeper investigation.

What information is needed to start?

A postcode, coordinates or site boundary, the project type, target live date and a basic description of what the connection needs to support are enough for an initial review.

Can one supplier provide both primary and backup connectivity?

It can, but the physical routes, underlying wholesale networks, nodes, power and operational dependencies must be checked. Two services on one invoice are not automatically diverse.

Apply this to a live site

You do not need to know the product before speaking to us.

Send us the site, project or carrier quotation and we will identify the most useful next step.